Monitoring the Deadlines Automatically
Use
The deadline monitoring function consists of a report that allows you to:
If you want to start the deadline monitoring function at regular intervals, you must predefine the selection criteria for executing this report in a report variant. In addition, you must
plan a background job to specify when or in what intervals the report should be run as a batch job.
You can also run this report for deadline monitoring manually as described in the procedure below, if for example:
Prerequisites
You have
defined the start date for the stability study.Procedure
The initial screen for deadline monitoring appears.
The Call Transaction mode is proposed by the system.

You can also select the BDC session mode, however, the system will then only create a batch input session and no calls will be created or test dates updated. To accomplish this, you must execute the BCD session separately from this operation.
The system generates test dates or inspection lots for the selected maintenance plan(s).

The test dates are normally confirmed automatically (by means of a follow-up action for the usage decision) when you complete the stability tests.