Entering content frameFunction documentation Scheduling in the Project Builder Locate the document in its SAP Library structure

Use

In the Project Builder you can schedule a project based on the network activities in the project.

Integration

The scheduling settings are taken from the profile for WBS scheduling. You can change the scheduling type, method, and parameters in the project planning board that you can call up from the Project Builder.

Prerequisites

To carry out scheduling in the Project Builder, you must have entered a start and finish date for the project definition.

Activities

In the structure tree select the project definition of the current project and choose Edit ® Dates ® Schedule. To change the scheduling parameters switch to the project planning board by choosing This graphic is explained in the accompanying text.

For more information on the various dates in the Project System, refer to Structure linkDates.

 

 