Entering content frameFunction documentationMaster Data in Purchasing Locate the document in its SAP Library structure

Use

Purchasing contains information for the procurement of a material or service from a certain vendor, such as conditions negotiated with the vendor. Costing enables you to access this information in the following areas:

Prerequisites

In order to access the prices from purchasing (that is, the purchasing info record or purchase order), you must enter the following in Customizing for Product Cost Planning:

Features

The link between material/activity and vendor is established in purchasing. It manages information about the vendor, and about the materials and activities that you have obtained from the vendor, such as quantities, prices, price changes, and other costs.

When costing, you can access information in the purchasing info record and purchase order, for the following purposes:

This enables you to carry out raw material costing. Instead of the price being taken from the material master, an actual cost estimate including overhead calculation for material components is executed. This cost estimate does not have a quantity structure (BOM, routing).

For more information, see Valuation of Subcontracting.

For more information, see Valuation of Externally-Processed Operations.

You can access the following prices:

You determine which activity price is selected by defining a valuation variant in Customizing for Product Cost Planning and assigning it to the costing variant.

The valuation variant contains a search sequence that has a maximum of three prices.

Example

You have defined the following strategy sequence for the valuation of external activities:

    1. Net quotation price
    2. Net order price
    3. Price from operation

If a net quotation price exists in the purchasing info record, the system transfers this price. If no such price exists, the system transfers the net order price from the purchase order. If no purchase order was created for the operation, the system uses the price in the externally-processed operation in the routing.

See also:

For more information about purchasing master data, see the following in the SAP Library under Structure link MM Purchasing:

For more information about performing costing, see the following:

Leaving content frame