Entering content frameProcedure documentation Picking HUs Manually (Process Order) Locate the document in its SAP Library structure

Use

For the production supply, you can pick ingredients manually in Structure linkhandling units (HUs). This includes

Picking is carried out using the reservation items of the process order.

Procedure

  1. Choose Picking in the PI sheet.

The Picking for Production Order screen appears.

  1. Enter the measured and packed materials for the process order.

Enter the following:

If you do not enter an HU number, the system creates a new one.

You can check which materials are assigned to the process order but not yet picked on the Open Reservations tab page.

Note

The Operation column

In the master recipe, a material can be assigned to an operation or a phase, in order to ensure the correct sequence in production. If a material is not assigned to a phase, the system automatically assigned it to the first phase of the process order. During picking, the material can then

  1. Packing the material:
    1. Select the material.
    2. Choose a Packaging material type.
    3. Choose Pack.
    4. An HU number is automatically assigned to the reservation item.

Note

The HU number can be assigned independently if an external number range assignment has been maintained in Customizing. The HU number must then correspond to this number range.

  1. Packing HUs in higher-level HUs for picking (for example on a pallet):
    1. Select a container hierarchy.
    2. Select the HUs to be packed.
    3. Choose a Packaging material type.
    4. Choose Pack.
  1. Assigning the HUs to the process order:
    1. Enter the higher-level HU in the input field.
    2. Choose Enter. The system gives a proposal for the material items in line with the reservation list.
    3. Enter your own data in place of the proposed values.
    4. Choose Assign.
  1. Deleting the assignment of HUs to the process order:
    1. Enter the higher-level HU.
    2. Choose Enter.
    3. Delete the assignment of HUs to the process order:
  1. Completing manual picking
    1. Choose Save.
    2. The PI sheet appears.

      The system conforms that picking was successfully carried out with y (yes).

      If picking was not successfully carried out, an error message appears.

    3. Enter a digital signature if the system requires one.

The picking data is transferred to the batch record. You can use the message monitor to check whether the messages were processed correctly. This is necessary if the system does not send the messages automatically.

For further information, see Structure linkR/3 Integration Using Process Messages

Note

Manual picking can be called up again after completion.

It is a good idea to pick parts of the materials at different times during production. For example, the materials for the first phase(s) can be completely picked, and the remaining materials can be partially picked.

Leaving content frame