Use

To reduce the lead time of a routing or production order you can overlap operations. This means that an operation starts before the previous operation has finished (see Overlapping graphic, for instance, operations 40 and 50).

This graphic is explained in the accompanying text

Overlapping

Features

You can define for each individual operation whether it should overlap with the next consecutive operation and in what way. To do this you can set the following indicators:

This means the operations always overlap

This means the operations overlap if scheduling uses a reduction level that allows overlapping

This means the system extends the lead time of all operations, that overlap using flow manufacturing, to the same length as the lead time of the longest of these operations. As with required overlapping, the operations always overlap.

For every type of overlapping you can

Activities

You enter the overlap indicator, minimum overlap time and minimum send-ahead quantity on the operation details screen.

 

 

 