Changing the Standard Value for Setup Manually
Use
You can manually change the setup times of selected operations in the planning tables.

This function is not available for capacity leveling in the process industry (PP-PI), that is, for capacity leveling of process orders and planned orders that refer to master recipes.
Prerequisites
Use only standard value keys for which the setup standard values are located at the same place (that is, for which the setup standard values have the same standard value number) for the work centers relevant for capacity leveling.
Procedure
In the capacity planning table (graphic) |
Functions ® Adjust setup time ® Manual |
In the capacity planning table (tabular form) |
Functions ® Extended planning ® Adjust setup time |
Procedure
The system reschedules the relevant orders, although it takes the new setup standard values into account.