Entering content frameProcedure documentation Changing the Standard Value for Setup Manually Locate the document in its SAP Library structure

Use

You can manually change the setup times of selected operations in the planning tables.

Note

This function is not available for capacity leveling in the process industry (PP-PI), that is, for capacity leveling of process orders and planned orders that refer to master recipes.

Prerequisites

Use only standard value keys for which the setup standard values are located at the same place (that is, for which the setup standard values have the same standard value number) for the work centers relevant for capacity leveling.

Procedure

  1. Select the operations for which you want to adjust the setup times.
  2. Choose
  3. In the capacity planning table (graphic)

    Functions ® Adjust setup time ® Manual

    In the capacity planning table (tabular form)

    Functions ® Extended planning ® Adjust setup time

  4. Enter the setup standard value for each operation with which the setup time should be recalculated.
  5. Choose Execute.

Procedure

The system reschedules the relevant orders, although it takes the new setup standard values into account.

 

 

 

 

 

 

Leaving content frame