Entering content frameObject documentation Schema TM00: Time Evaluation Using Time Events Locate the document in its SAP Library structure

Definition

Schema TM00 is a standard schema, used to evaluate employee time data that has been recorded at time recording terminals and that specifies clock times.

Structure

Schema TM00 is based on the following requirements and objectives:

Schema TM00 forms time balances, time wage types and time quotas. It is processed using the time evaluation report RPTIME00.

Schema TM00 processes the personnel time events recorded at the terminals and the time pairs formed from these events. It also imports and processes time data that has been entered online.

When time data is processed with schema TM00, all times to be included in working time (actual times) must be recorded.

Time data must be entered as clock times and must be full-day records.

The main function of schema TM00 is to classify the actual times by comparing them with the planned working time data stipulated in the daily work schedule (planned working time start and end, core times, break times).

When calculating overtime, schema TM00 does not recognize the times before/after the start and end of planned working time as overtime if no approval has been given.

Overtime approval can be granted in individual steps. In schema TM00, you can select from the following checks:

In all of the above cases, overtime is calculated only:

This schema contains examples for calculation of daily and weekly overtime.

 