Entering content frameFunction documentation Priority for Different Effectivity Types Locate the document in its SAP Library structure

Use

An object (for example, a BOM item) can be processed with reference to different change master records.

It may be that the following conditions prevail:

If this is the case, the priority of the effectivity type determines which change is taken as effective.

Features

The priority of an effectivity type determines whether the change is taken as effective. The likelihood of a change being taken as effective increases with priority.

Activities

  1. In Customizing for Engineering Change Management, choose the Parameter effectivity ® Define effectivity types step.
  2. Enter the priority for one or more than one effectivity type.
  3. Save your entries.

See: Example: Changes with Different Effectivity Types