Entering content frameProcess documentation Goods Issue for the Delivery Locate the document in its SAP Library structure

Purpose

Inventory Management uses this process in such a way that the goods issue posting is divided into two parts that run in separate systems. Posting the GI document in the supplying plant results in a message to the receiving plant. The receiving plant then performs a complementary posting. The physical goods receipt takes place as usual.

Prerequisites

When using batch processing, the following prerequisites must be fulfilled:

Characteristics

Process Flow

Goods Issue Posting for Stock Transfers

The delivery triggers the goods issue in the issuing system.

The call contains the stock transport order data known in the delivery, including the PO item and the logical system of the recipient.

The transaction (quantity and value updates) is selected using the movement type:

Movement Type

Function

641

Goods issue with UB logic (Creation of stock in transit at recipient, immediate value posting).

647

As 641, however the goods receipt line (movement type 101) is added automatically, so that the goods receipt is posted at the same time as the goods issue (one-step procedure).

You determine the movement type according to the schedule line category in Sales and Distribution. The goods issue for a cross-system stock transfer must be different from the integrated transaction. This is achieved by adding a new movement type.

You post quantities and values at goods issue in the same way as a goods issue for a sales order. That is to say, the quantity is posted in the supplying plant and the value is adjusted to that of the stock account. The offsetting posting is made to a clearing account. The known data from the delivery is copied to Accounting to balance the account where necessary.

The system creates a message to the appropriate receiving system for all items with reference to a cross-system purchase order. The system does not perform any validity checks on the recipient’s data before posting begins. Incorrect Customizing results in the update being terminated.

If a goods issue has receiving plants in different logical systems, an IDoc is sent for each system.

In order that the goods receipt is able to use the values on the receiver side, you must add the values used to post the goods movement, in particular the transfer prices, to the IDoc.

The logic for recognizing the profit center switch functions as follows: At goods issue, the system recognizes that the profit center of the issuing plant is different from the profit center of the receiving plant. The system derives the profit center node from the relevant profit center.

Data Transfer

The IDocs sent by the issuing plant trigger the goods issue postings in the receiving plant.

Background Posting in the Receiving System

The goods receipt is posted in the receiving system using the IDoc. The interface receives the data from the goods issue in the supplying plant. The following processes now run at the recipient:

Reversal

You can only reverse this goods issue for the PO using the cancellation transaction in SD. You cannot reverse the GI in Inventory Management.

The material document that is automatically created in the receiving system cannot be canceled. This reversal is triggered by the sending system (the actual reversal of the GI document takes place there) and transmits the data, including the reversal movement type, to the receiving system. No actual reversal is posted in the receiving system, because the material document number of the original document does not exist in this system. This scenario is applicable for cases where you use the two-step procedure (with stock in transit).

Distribution of Batch Master Data and Characteristics

Shipping Notification

The shipping notification is required in the receiving system due to its relevance for MRP. In this way, for example, a change in delivery date determined at goods issue is sent to the receiving system using the shipping notification. The shipping notification can also be used when posting the GR batches.

 

 

Leaving content frame