By scheduling routings, you can better control the lead times. When you create a routing, it is already possible to check the expected lead time and if necessary adjust the routing.
Routings are scheduled without reference to an order.
Proceed as follows to schedule a routing:
You reach the Scheduling dialog box.
You reach the Enter overview variant dialog box.
The routing is scheduled. You reach the Schedule Overview screen containing the scheduling data.
You can also schedule all routings in a group at once. You can find further information on this topic in
Updating the material master recordsSee also:
Sources of error: What to do if...?