Entering content frameProcedure documentation Releasing Standard Cost Estimates Locate the document in its SAP Library structure

Prerequisites

Caution

Before you release a standard cost estimate, make sure that the future standard price is correct, since you can only release once per period. As soon as the cost estimate has been released for a material in a company code, you cannot repeat the standard cost estimate, marking or release in this posting period.

Recommendation

Check the costing results before you release the standard cost estimate. You can use the Information System reports to compare the cost estimate price with the current standard price and display variances. For further information, see the following:

Procedure

  1. Choose Accounting ® Controlling ® Product Cost Controlling ® Product Cost Planning ® Material Costing ® Price Update.
  2. The screen Price Update: Mark Standard Price appears.

  3. Choose This graphic is explained in the accompanying text Release.
  4. The screen Price Update: Release Standard Price appears.

  5. Enter the posting period and fiscal year.
  6. Restrict the cost estimates to those you want to release.
    1. You can restrict the selection to company codes, plants, and/or material numbers.
    2. If required, choose This graphic is explained in the accompanying text to select a variant for the selection of cost estimates.
  1. By turning the indicator on or off, you determine whether:
  1. Choose This graphic is explained in the accompanying text to execute the release.

Note

If you have set the indicator Background processing, release is not carried out immediately. The system next displays the dialog box Background Processing: Job Parameters.

Set the indicator Immediate start if you want to start the release immediately in the background, or enter the date from which the job should be started. Choose

For more information, see Background Processing.

Result

When you have released the standard cost estimate, the corresponding future standard prices are updated as the current standard prices in the material master. How often you release a standard cost estimate depends on its planned validity period. If stocks of materials exist, the stock value changes and a document is created in Financial Accounting documenting the price change. For further information, see Structure link Document Display.

If you carried out the release online but did not set the indicator With list, the system issues a message containing the information as to how many standard cost estimates were released successfully or had errors.

If you carried out the release online and set the indicator With list, the system displays a list of materials that were released or, in the case of a test run, will be released. This list can easily be adapted to suit your requirements. For more information, see Functions of the ABAP List Viewer.

To return to the screen Price Update: Mark Standard Price, choose This graphic is explained in the accompanying text in the application menu. If you choose This graphic is explained in the accompanying text Log in this screen, you can call the log which you last generated once again.