Use
Internal activities are displayed in the cost estimate as category E items. The quantities used for such an internal activity are determined using the entries in the operation of the routing for the Cost Estimate with Quantity Structure or specified using your manual entry for the Unit Costing.
A price from Cost Center Accounting is used to valuate this activity quantity. You determine which price is used to valuate the internal activity in the cost estimate via the valuation variant in Customizing. It is possible for you to use for instance the plan price of the period or the actual price of the previous period to value the internal activity.
Procedure
You must enter version 000 (operative version) for the standard cost estimate. For inventory costing, you can use other plan/actual versions.
See also:
CO Overhead Cost Controlling