Definition
List of all operations in the routing.
Use
The following information in the operation overview is relevant for costing:
Work center
The system selects the following data through the work center:
-
Formulas that access default values to determine the planned times-
Activity types for which activity prices are planned or determined in Cost Center Accounting-
Business processes for which prices are determined in Activity-Based CostingControl key
The control key specifies, among other things,
– Whether the operation is included in the cost estimate
– Whether the operation is processed internally or externally
– Whether and how the operation is confirmed
Suboperations are handled in the same way as operations.