Entering content frameObject documentation Multilevel BOM Locate the document in its SAP Library structure

Definition

BOM containing materials that have their own BOMs (assemblies)

Use

The system assigns a low-level code (the Logistics view) to each level of the BOM. The following graphic shows a multilevel BOM and its low-level codes:

This graphic is explained in the accompanying text

The system explodes the BOM from top to bottom (low-level codes), and assigns costing levels (from the costing view). The following graphic shows a multilevel BOM and its costing levels:

This graphic is explained in the accompanying text

The costing levels determine the sequence in which the cost of goods manufactured is calculated for each material.

This ensures that the costs for all assemblies and all raw materials or purchased parts are included in the costs calculated for the end product. This process is also called cost rollup. A cost component split is created for each assembly costed, grouping the costs into, for example, material costs, production costs, and overhead. For raw materials or purchased parts, you can create an initial cost split to break down the procurement costs.

When you save the cost estimate for the end product, a cost component split for each level of the cost estimate is saved as well. This enables you to analyze the value added at each production level.

See also: