Entering content frameFunction documentation Changing, Cancelling, & Blocking Outl. Agreements Locate the document in its SAP Library structure

Use

You can change, cancel, and block outline purchase agreements.

Prerequisites

Before changing or cancelling an outline agreement, you must consider the following:

When you change an outline agreement after it has been sent to the vendor, a change document (change notice) is automatically generated and queued for printing or transmission. The change document tells the vendor what you have changed in the outline agreement.

If goods have already been delivered, then the changes you can make to the outline agreement are limited. For example, you cannot change the quantity to deliver in a quantity contract to an amount that is less than the amount already delivered.

If the invoice has been received or the goods have been paid for and you change the price, the change has no effect. (The vendor must send an invoice for the new amount or credit your account.)

You can view the ordering activity for a contract item by displaying the release (order) documentation for the item.

You can "block" an outline agreement to freeze all activity on it. After the implementation and checking of desired changes, you can unblock the agreement again.

 

 

 

Leaving content frame