Entering content frameProcedure documentation Creating a Delivery Schedule for an RFQ Locate the document in its SAP Library structure

If the desired quantity is to be delivered according to a prearranged schedule, you can enter each desired delivery date (and time if you wish) in schedule lines (e.g. 20 pcs. on 5 May 1998 at 10.00 hrs., 30 pcs. on 6 May at 10.00 hrs., etc.). You enter this data in the delivery schedule for the relevant PO item.

  1. Select the desired item in the item overview.
  2. Choose Item ® Delivery schedule.

The screen for entering schedule lines for the item appears.

  1. Enter the delivery date, the delivery time-spot, and the scheduled quantity for each delivery. You can specify the delivery date as a calendar day, week, or month.

The section Outline Agreements with Vendors contains detailed information on the subject of delivery schedules created under scheduling agreements.

 

 

 