Entering content frameFunction documentation Allocating Plan Values in an Actual Allocation Cycle Locate the document in its SAP Library structure

Use

You create separate cycles for plan and actual allocations.

In segment definition, however, you can define that the plan costs are allocated in the actual instead of the posted actual costs. To do this, choose Plan values during segment definition.

This ensures that the actual costs are allocated just as the plan costs. The system ignores any plan allocations that have already been executed.

Note

In actual assessment or actual distribution using plan values, the system does not consider any costs arising through plan assessment or plan distribution. Instead, the system uses amounts from actual assessment or actual distribution.

 

 

 