Entering content frameFunction documentation Requirements for Indirect Activity Allocation Locate the document in its SAP Library structure

Use

You enter the actual activity quantities of category 3 by choosing Non-allocable activity.

Note

You can only plan activity quantities using activity type planning for activity types of activity category 3. For activity types of category 2, this field is not ready-for-input in activity type planning. This is because the system determines the activity quantities inversely from the receiver tracing factors or using fixed quantities. In this case, the system automatically determines the corresponding planning record of cost center/activity type.

Note

If you carry out indirect activity allocation without completing planning for the combination cost center/activity type, you must select the actual price indicator in the activity type master data if you want to use actual prices.

 

 

 