Use
You use transfer control to assign individual material components to another WBS element.
Transfer control has two functions:
Procedure
If the component is kept in
If you want the requirements of the corresponding components to be consumed(if they are in project stock),they must both be assigned to the same WBS element, since
requirements consumption takes place only within the same stock segment and not across projects.