Entering content frameProcedure documentation Assigning Material Components to Other WBS Elements Locate the document in its SAP Library structure

Use

You use transfer control to assign individual material components to another WBS element.

Transfer control has two functions:

Procedure

  1. Choose Logistics or Accounting ® Project System ® Material ® Planning ® BOM transfer.
  2. Choose This graphic is explained in the accompanying text Transfer.
  3. Enter the material and the WBS element that you want to assign the material component to.
  4. Save your data.

Note

If the component is kept in project stock , the system also changes the stock segment.

If you want the requirements of the corresponding components to be consumed(if they are in project stock),they must both be assigned to the same WBS element, since requirements consumption takes place only within the same stock segment and not across projects.

 

 

 