Entering content frameProcedure documentation Maintaining Billing Plans for WBS Elements Locate the document in its SAP Library structure

Use

You use the billing plan to plan the dates on which payment requests or invoices affecting sales are sent to customers.

Prerequisites

If you want to maintain a billing plan for a WBS element, you must flag that WBS element as a billing element.

You must maintain a revenue element in the plan profile. The system records revenues and incoming payments under this revenue element.

If you want to use templates to create billing plans, go to Project System customizing and maintain a billing plan in the Maintain Billing Plan Type transaction.

Note

The standard system we deliver contains billing plan type 31 as a template. You can create the billing plan template directly in the implementation guide or copy a billing plan already in the WBS element to act as your template. The template contains dates, percentages, and absolute amounts.

Procedure

  1. Call up the WBS element overview in WBS maintenance.
  2. Select the relevant WBS element and choose This graphic is explained in the accompanying text Details ® Billing plan.
  3. The Billing Plan dialog box may appear. Choose a billing plan type and currency type and enter a target value.

    This takes you to the screen for changing dates in the billing plan.

  4. Enter the necessary data.
  5. If you want to work with a template, enter the number of the relevant billing plan template in the Template field. You can have the system display all the templates you have maintained in Project System customizing.

    Note

    You must always enter the template number as a ten-digit figure. For example, if the template number is 491, you must enter 0000000491 in the template field.

    The system displays the dates and percentage apportionments, updated, in the billing plan. You can overwrite this data.

  6. Choose This graphic is explained in the accompanying text to return to WBS maintenance.
  7. This brings you to the WBS maintenance screen.

  8. Choose This graphic is explained in the accompanying text to save the WBS.

This saves the billing plan too.

Result

The system determines the planned revenue and incoming payment data from the billing plan and updates it to the relevant WBS element. This takes place in plan version 0 and commercial transaction PSFP.

The revenue-relevant dates in the billing plan update the WBS element revenue plan periodically. Plan data is recorded under the revenue element for the plan profile given in the project definition. Down payment dates are not so recorded because they are not revenue-relevant.

If you have activated Project Cash Management, the billing plan data updates the WBS element financial budget daily, taking account of the payment terms entered for that date. .

See Structure linkCalculating the Payment Flow Automatically.

If you are working with a template, the system determines the dates and percentage distribution of amounts per that template. The system adapts the dates and percentage apportionments to the target date. If you change the start date, the billing dates are adjusted accordingly.

Note

The advantage of working with templates is that the dates in the billing plan are adjusted automatically if the dates in the WBS change. Note that the dates in the billing plan are not updated until the WBS has been scheduled.

If you want to work with fixed dates, you must not use templates to create your billing plan.

Example

Updating the Revenue Plan

Billing Plan for WBS Element

Items in Billing Plan

Date

Amount in $

Down payment date

01.01. 1998

1 000,00

Assembly

01.03. 1998

7 000,00

Production startup

01.05. 1998

3 000,00

 

Values are updated to the revenue plan under the revenue element defined in the plan profile. Down payment dates are not revenue-relevant and do not update the revenue plan.

Revenue Plan

Period

Amount in $

Assembly

03

7 000,00

Production startup

05

3 000,00

 

 

Leaving content frame