Creating Material PRTs
To create a production resource/tool as a material, create a material master in which you maintain the
Production resources/tools view. The PRT data are plant specific.For more information about maintaining material master data, refer to the
Material Master component LO-MD-MM).or
Logistics/accounting ® Project System ® Basic data ® Master data ® Material ® Create.

In the second case do not choose Production resources and tools. This would create a PRT master record (see Creating PRT Master Records), and not a material master.
The initial screen for creating a material appears.
2. Enter the relevant data on the initial screen.

To create a material PRT you must enter a material type which allows you to maintain the Production resources/tools view. One such material type is FHMI. If you want to change the material type of a PRT, the new material type must have the Production resources/tools view.
3. Choose Continue.
The Select Views dialog box appears.
4. Select the Prod. Resources/Tools view and choose Continue.
The Organizational Levels dialog box appears.
5. Enter the plant to which the production resource/tool is assigned and choose Enter.
The Create Material: Prod. Resources/Tools screen appears.
6. Maintain the basic data and the default values for task list allocation.

If you have allocated a PRT to an activity, you can no longer change the base unit of measure and the unit of issue in the master record.
7. Save the material.