Entering content frameProcedure documentation Copying Project Objects Locate the document in its SAP Library structure

Use

In your current project you can use WBS elements, activities, activity elements, and milestones as templates for new project objects and copy them in the project.

Features

The various options for copying are listed below:

Function

Action

What You Should Know

Copy WBS elements

Select a WBS element in the table area and choose This graphic is explained in the accompanying text

or in the context menu choose Copy.

Then choose This graphic is explained in the accompanying text.

In the context menu choose Paste.

Copies one or more WBS elements from the current project as new WBS elements to a new position. To insert a WBS element, select another WBS element.

Copy activities

Select an activity in the table area and choose This graphic is explained in the accompanying text

or in the context menu choose Copy

Then choose This graphic is explained in the accompanying text.

In the context menu choose Paste.

Copies one or more activities in the current project to a new position. To insert an activity, select a WBS element.

Note

You can also copy assignments to an activity with the activity (e.g. long texts and milestones). However relationships are not copied.

Copy activity elements

Select an activity element and choose This graphic is explained in the accompanying text

or in the context menu choose Copy.

Then choose This graphic is explained in the accompanying text.

In the context menu choose Paste.

Copies one or more activity elements in the current project to a new position. To insert activity elements, select an activity.

Copy milestones

Select a milestone and choose This graphic is explained in the accompanying text

or in the context menu choose Copy.

Then choose This graphic is explained in the accompanying text.

In the context menu choose Paste.

Copies one or more milestones in the current project to a new position. To insert a milestone, select a WBS element or activity.

Note

After you have inserted copied project objects, you can delete them from the project structure by using the Undo function. Choose This graphic is explained in the accompanying text or Undo in the context menu.

 

 

Leaving content frame