Entering content frameProcedure documentation Simulating Changes in the Scheduling Overview Locate the document in its SAP Library structure

Use

In the simulation mode of the scheduling overview, the graphical maintenance plan simulation of the scheduling overview, you can simulate certain changes to the information displayed at maintenance plan level.

This is very useful if you want to see the effect that shifting call dates has on the maintenance plan, or if you want to level off the capacity load interactively in the individual work centers.

The following table shows the functions possible for maintenance calls in the maintenance scheduling overview:

 

Call

Postpone/Fix

Ignore

Single cycle plan

X

X

X

Strategy plan

X

X

X

Multiple counter plan

X

 

X

 

Possible Simulated Changes

You can simulate the following changes at maintenance plan level:

You can shift dates provided that the call sequence is maintained. You cannot skip over earlier or later call dates. You can:

You can change the status to:

You can change the status to:

Simulating Changes

  1. Call up the scheduling overview directly from the maintenance planning menu.
  2. If you are already in the graphical maintenance item overview (and have called it up directly), you can switch to the maintenance plan simulation. To do this, choose Environment ® Maintenance plan simulation.

  3. You reach the maintenance plan simulation graphic.
  4. Using the Edit menu, you can simulate the following changes:

For multiple counter plans, you can change the status, but it is not possible to simulate scheduling.

Resetting Simulated Changes Again

If you do not want the changes you have simulated to be transferred, you can:

The simulated changes are not saved.

The original call dates are restored, and the colored boxes reassigned their original color.

Saving Simulated Changes

If you want to save the changes you have simulated, choose Graphic ® Save.

The simulated changes are saved immediately. For example, if you have shifted a call date, the new (shifted) date becomes the new call date when you save, and is indicated accordingly in the graphic.

 

 

Leaving content frame