Time-Based Scheduling
If you create a monthly maintenance cycle (one month = 30 days) and have specified time-based scheduling, planned dates are calculated as follows:
|
Current Date |
21. August, 1999 |
|
1st planned date |
20. September, 1999 |
|
2nd planned date |
20. October, 1999 |
|
3rd planned date |
19. November, 1999 |
Planned dates are therefore created every 30 days.