Entering content framePreliminary Buffer Locate the document in its SAP Library structure

The preliminary buffer specifies how long before the due date for the maintenance package the activities can be started, without the subsequent due dates being changed.

Example

You specify a preliminary buffer of 5 days for each maintenance package in the strategy.

The planned date calculated by the system is September 30. The start date proposed in the maintenance order is therefore September 25.

 

Leaving content frame