Use
The creation profile determines:
The tolerance check is only carried out if lines of the overall schedule for an item have been changed and if you create SA releases using the release creation program (via Scheduling agreement ® Create SA release).
Features
A creation profile is defined on a plant-dependent basis and consists of the following areas:
Tab page |
Here you define the following, depending on the scheduling agreement release type (FRC or JIT delivery schedule): |
General parameters |
|
Aggregation horizons |
If your creation profile provides for aggregation, quantities and delivery dates set out in the lines of the overall delivery schedule stored in the system for a scheduling agreement are aggregated to form release schedule lines. If you use a creation profile without aggregation, or work without a creation profile, the schedule lines of the SA release correspond to the schedule lines of the overall delivery schedule for the scheduling agreement for the relevant period. |
Creation periodicity |
Each time a scheduling agreement release is created, the system calculates the next creation date. Weekly and monthly releases are always created on a Monday (first workday of the period). The system takes the factory calendar as the basis for calculating the due dates for release creation. If you wish to create SA releases on a periodic basis, you should choose a creation strategy that includes Next date. |
Tolerance profile |
In the case of SA releases containing backlogs or immediate requirements, the system never checks tolerances. |
Activities
You process creation profiles in Customizing for Purchasing under Scheduling Agreement ® Maintain Release Creation Profile for Scheduling Agreement with Release Documentation.
You assign a creation profile to a scheduling agreement item in the Additional data.