Down Payments
Use
Down payments made for investment measures represent acquisition postings. They are usually identified by a separate cost element.
Features
You have to post the following transactions in conjunction with a down payment:
Account Assignment
The FI component provides the transactions necessary for account assignment of down payments to an order or project.
Along with direct account assignment to orders or projects, it is also possible to have account assignment of down payments to purchase orders. These purchase orders are then assignable to the order or project.
System Settings
You need to make the settings and create the master data outlined below. Once you make these entries in Controlling (CO), it is possible to update down payments that have account assignment to orders or projects.

Since primary cost elements cannot be balance sheet accounts, direct account assignment to the special general ledger accounts of Accounts Payable, or the reconciliation accounts of Asset Accounting is not possible. These accounts are posted only when you carry out periodic settlement of the investment measure to its accompanying asset under construction.
You have to make the following settings in Customizing in the FI-AA component, in order to post down payments to assets:
Full Settlement
At the time of full line item settlement, make sure that the down payment and clearing of the down payment are settled together using the same settlement rule. Using this procedure guarantees that the down payment and the clearing of the down payment also balance to zero on the settlement receivers.
Graphic: Full Settlement of Down Payments
If you are using foreign currencies in Asset Accounting, you have to post the down payment and the clearing of the down payment with the same translation date (value date). In this way, you ensure that changes in currency valuation have no effect on the balancing of down payments and the clearing of down payments.
Down payments cannot be transferred from a network to a WBS element. If you want to make account assignment of down payments to an investment measure, then always assign them directly to the WBS element. You can then settle the down payment from the WBS element to the accompanying asset under construction.
Procedure
Posting Down Payments