Distributing Budget to Measures
Procedure
Choose Budgeting ® Budget distribution ® Edit.
Enter the program position, to which the investment measure you want to work with is assigned. You could enter a program node instead. The system then selects all end nodes of the program that are below the node you selected, along with their measures.
Select the measure type you want to process (order or WBS element).
Specify the type of activity you want - either distribution of original budget, supplements or returns.
Choose Execute. The system displays all measures for the program position you entered.
Assign the supplements/returns for the overall budget or the annual budget of the assigned measures. These supplements/returns change the assigned value of the program positions they are assigned to.