Activating Availability Control Online
Course Prerequisites
In the budget profile, you chose activation type 2 (background activation) for availability control
Background activation for availability control checks whether or not the usage level defined in the budget profile has been reached. If the usage level is exceeded, availability control is activated.
You can start the batch run for availability control automatically.
In The Project System (Same Procedure as for Internal Orders)
In the project system, select the projects that you want to start in the batch run.

Background activation of availability control logs the objects for which you activated availability control. If you set the Detailed Log indicator, the system also displays all projects of the specified variant (object selection) for which you did not activate availability control.
Job Definition
You can start the batch run for availability control using a job definition.