Activating Availability Control Online
In the budget profile, you chose activation type 2 (background activation) for availability control. However, you can activate online availability control for one project.
You can activate availability control for a project before the usage level is reached or before the next batch run.
In The Project System (Same Procedure as for Internal Orders)
You activate online availability control as follows:
The Change Original Budget: WBS Element Overview screen appears.
The system issues a message confirming activation.

Availability control is activated the next time you choose Save or Check. After activation, every posting in the project is checked by the availability control.

If you now reduce the budget and the assigned funds exceed the tolerance limit of availability control, the system refers you to the error log when you check or save the budget.