Procedure
The Scheduling dialog box appears.
The Enter Overview Variant dialog box appears.
The Scheduling Overview for the routing appears.
The Scheduling Results dialog box appears. Here the newly scheduled lead times are listed together with the lead times specified in the material master record. In addition, the lot size from scheduling is shown across from the base quantity in the material master record.
You can carry out scheduling several times in a routing (for example, with various lot sizes). The results from each scheduling run are stored in a temporary file.
If you do not see the function key Update mat. master on the dialog box, you did not enter the material on the initial screen for routing maintenance. In this case, repeat steps 1 through 4.
Result
The system saves the scheduling results together with the calculated assembly scrap in the temporary file. You can update the relevant material master record now or later.