Entering content frameConceptual documentation Defining a View for BOM Explosion Locate the document in its SAP Library structure

You can use the following indicators to influence the BOM explosion:

Alternative priority

When you explode a BOM, this indicator determines that the system only searches for the alternative you enter in the Alternative field in multiple BOMs.

Example

Material A has a multiple BOM, as shown in the following graphic:

 

This graphic is explained in the accompanying text

The following table illustrates two different explosions of this multiple BOM, produced according to different selection criteria.

Explosion with Alternative Priority

Your selection criteria in these fields

Produces an explosion as follows:

Alternative: 03

Alternative priority: X

Explosion continuously to level 2

   

Alternative: 02

Alternative priority: X

Only to level 1

 

Scrap

This indicator affects how the component quantity is calculated as regards scrap values. If you want to take scrap into account, the system increases the required quantity by the scrap factor defined. If this puts the required quantity in a different lot size, the system determines a different alternative, provided that the material master supports selection according to order quantity (View MRP 2, Alternative selection field, value Blank).

The following scrap values are relevant:

If assembly scrap is maintained for an assembly in its material master, the system applies this scrap factor to all components of the assembly (with the exception of components that have operation scrap). Component scrap only affects an individual component.

Example

Material A has an assembly scrap factor of 10 % and a multiple BOM with the following alternatives:

Alternatives with Lot Size

Alternative

From lot size

To lot size

01

1

1000

02

1001

2000

 

The required quantity entered for the BOM explosion is 1000.

If you do not take scrap into account, the system explodes alternative 01. If you set the scrap indicator, the required quantity is increased by the scrap amount (1000 + 100), and the system explodes alternative 02.

Sort

For a summarized BOM, you can enter a sort procedure in this field for the BOM components. You can sort the components according to the following criteria:

Example

The following overview shows the components of BOM A.

Components of BOM A

Item number

Component

Quantity

Sort string

0010

B

12

Bolt

0020

B

10

Bolt-01

0030

D

10

 

0040

E

10

 

0050

F

30

Bolt

 

If you do not take the sort string into account (Sort string field with value Blank or 1), items 0010 and 0020 are displayed as one item with a sum quantity of 22.

If you do take the sort string into account (Sort string field with value 2), items 0010 and 0020 are displayed separately. The system sorts the items in ascending order according to the sort string (0030, 0040, 0010, 0050, 0020).

 

 

 

 

Leaving content frame