Entering content frameFunction documentation Data for Alternative Items Locate the document in its SAP Library structure

Use

When you enter an alternative item group for the item, you can enter the Priority, Strategy, and Usage Probability in a dialog box.

Features

Usage Probability

Material requirements planning (MRP) plans the alternative items according to usage probability.

If you use the usage probability to determine the withdrawal posting (strategy 1), the quantities are proposed according to the usage probability. You can change the proposed quantities.

The component with the quantity 0 is displayed in the planned order. If required you can increase the quantity there.

Priority

The priority of an item within an alternative item group determines the sequence in which material components are reserved in the production order.

Strategy

The strategy is only relevant to the withdrawal posting in the production order. The strategy is ignored in MRP.

You use the strategy to determine how the items within an alternative item group are selected for the withdrawal posting. Use the same strategy for all alternative items in an alternative item group.

The following strategies for withdrawal postings are supported:

 

 

Leaving content frame