Executing Predistribution of Fixed Costs
Prerequisites
You can store a default value for this purpose in the activity type master data (see:
Processing Activity Types ). For business processes, you can store a default value in the business process master data or define a value for the business process category (see:
Fields in the Business Process Master Record)
You can overwrite the default value there (see
Activity Type Planning) or
Planning Process Outputs (Quantities and Prices)) In planning itself, you can change the fixed cost predistribution indicator only if no actual cost postings exist.
You can carry out fixed cost predistribution either as part of
plan price calculations or in a separate allocation for selected cost centers or business processes, for cost center groups or business process groups, or for the entire
controlling area.
Procedure
Executing Predistribution of Fixed Costs as Part of Plan Price Calculation
You can execute the actual postings for fixed cost predistribution as part of your plan price calculations.
Plan Price Calculations).
Executing predistribution with price calculation results in better system performance because the corresponding plan allocations already exist. Activity types with manually-set prices also take part in fixed cost predistribution when executed with plan price calculations.
Executing Predistribution of Fixed Costs as a Separate Allocation
You save selection criteria for cost centers in a
To create new selection variants, choose Goto ® Selection variant ® Create.
To change an existing selection variant, choose Change selection variant.
To display an existing selection variant, choose Display selection variant.
The detail list display uses the
ABAP list viewer.Reversing Predistribution of Fixed Costs

Reversing fixed cost predistribution is useful only if an error occurred during the posting. Carry out the reversal only if you really want to reverse all postings.
To reverse predistribution for the period entered, on the Predistribution of Fixed Costs: Cost Centers screen, choose Extras
® Reset.Result
The system allocates the plan fixed costs in version 000 as actual costs on the plan receivers (cost center or business process) for the activity types of a cost center or for the sender business processes participating in predistribution of fixed costs.
You can repeat predistribution of fixed costs as often as you wish. If you do so, the system updates only the difference between the old and new allocation. If the values do not vary from the previous allocations, the system does not update any values.