Creating an Operational Project 
Use
You create a project structure for the power plant for planning and costing a quotation.
Since your company usually manages the construction of power plants by using projects, a standard project structure already exists in the system. All you have to do is to adapt this standard structure to suit the specific requirements of your current project. To do this, copy the standard project into an operational project.
Use the Project Builder to create the project. You can find further information in the SAP Library under Logistics ®
Project System ® Structures ® Project Builder.Prerequisites
Standard project A-20000 is available.
The following settings have been made in Customizing for Project System:
Procedure
Menu Path |
Logistics ® Project System ® Project ® Project Builder |
Transaction Code |
CJ20N |
Field |
Data |
Standard project definition |
A-20000 |
The Create Project dialog box appears.
Field |
Data |
Project def. |
A-20### |
Description |
Power Plant A-20### |
Finish date |
Today´s date + 4 yaers |
Project profile |
Empty |

The finish date corresponds to the desired delivery date from the inquiry/RFQ.
The first release milestone is triggered when you create the project.
You can now see various objects in the structure display that have been copied from the standard project.
Project definition
WBS elements
Activities
Milestones
Result
When a project is created, the release milestone Release activities (in activity Plant engineering of WBS element Basic Engineering) releases all activities up to the next release milestone Down payment (in activity Acceptance of WBS element Basic Engineering).