Checking Material Availability of the Assigned Components
Use
When you assigned the task list to the maintenance order, you assigned not only the operations contained in the task list, but also the material components. You now check the availability of these material components.
Procedure
Menu Path |
From the Maintenance Processing node, choose Order ® Change. |
Transaction Code |
IW32 |
The system defaults your order number.
A material component is assigned to operation 0070. You can see this in the Components column.
On the Confirmation Proposal screen, the system informs you whether the material will be available on the required date. The open quantity equals 1 and the confirmed quantity for the required date is also 1. The checked material is available when required.
The Change Maintenance Order <Number>: Operation Overview screen appears.