Use
The system has defaulted an order start date and an order finish date. You now want to schedule the order precisely. You begin by setting the start date one week from today. You also need to allow for the execution. The scheduling also determines when each operation can start.
Procedure
Note the scheduled order start and finish dates.
Field |
Data |
OrderStart |
Today’s date + 7 days |
You can now check the results of the rescheduling. The scheduled start date has changed, and a date has been entered in the finish date field.
Operation 0070 is still selected on the screen.
You can see the scheduled dates for the operation on screen.