Checking the Capacity of the Work Center 

Use

Each work center has an available capacity. When you plan your maintenance orders, you need to match capacity requirements with the available capacity. In this process step, you check the percentage available capacity required by your maintenance order.

Procedure

  1. Use the following procedure to call the transaction:
  2. Menu Path

    Maintenance Processing ® Capacity Requirements Planning ® Evaluation ® Work Center View ® Load.

    Transaction Code

    CM01

  3. Enter the following data:
  4. Field

    Europe

    North America

    Description

    Work center

    MECHANIK

    MECHMNT

    Mechanical maintenance

    Plant

    1000

    3000

     
  5. Choose Standard overview.
  6. On the Capacity Planning: Standard Overview screen, you can see both required and available capacity.

  7. Choose until the overview tree appears.