Creating an Order and Selecting the Maintenance Task List 

Use

You now create an order from the notification and assign a maintenance task list to execute the planning.

Procedure

  1. On the Change PM Notification: Malfunction Report screen, to create an order, choose .
  2. To confirm the default values in the dialog box, choose .
  3. Choose Extras ® Task list selection ® General task lists.
  4. Enter the following data:
  5. Field

    Data

    Description

    Assembly

    WL-1000

    Pump shaft assembly

  6. To generate a list of all available task lists, choose .
  7. In this case, however, only one task list exists. It is assigned immediately.

  8. If the Operation Selection Using Work Center/Replace Work Center dialog box appears, choose All. Otherwise, proceed with step 8.
  9. This ensures that the work centers of the task list that are stored in the individual operations are copied into the order.

    The Operation selection dialog box appears.

    The entry in the Task list factor or Fct field for the individual operations shows how often an operation needs to be repeated.

  10. Choose All.
  11. The system copies the task list, including all its operations, into the order.

  12. Choose the Operations tab page.
  13. Select operation 0070 and choose Internal.
  14. In the Work field you can see the capacity requirement for the operation.

  15. Choose .
  16. Do not leave this screen.