Processing the Maintenance Order
Use
This process step describes only the basic steps that are required for further processing of the maintenance order. For a more detailed and complete description of the processing of maintenance orders, use the scenario provided.
Procedure
Menu Path |
From the Plant Maintenance node, choose Maintenance Processing ® Order ® Change. |
Transaction Code |
IW32 |
The system defaults the order number.
The Change Calibration Order ####: Central Header screen appears.
You now see the relationship between the order and the maintenance plan and to the task list.
The system releases the order when you save your entries. (Do not save just yet).
We describe order processing in another process. In this process, you technically complete the order immediately. This has no effects on further processing.
Your order has been saved. When you complete the order, the system updates the confirmation date in the maintenance plan. This is then used as the basis for additional scheduling activities.