Displaying Planned Changes 

  1. Call up the transaction as follows:
  2. Menu Path

    From the Materials Management node, choose Material Master ® Material ® Display Changes ® Planned Changes

    Transaction Code

    MM14

  3. Enter the following data:
  4. Field

    Europe

    North America

    Material

    1300-520

    1300-520

    Change number

    No selection

    No selection

    Plant

    1000

    3000

    Changes scheduled until

    Two weeks from today

    Two weeks from today

    If necessary, delete the entry in the Change number field.

  5. Choose .
  6. The system displays all the changes scheduled to take place on or before this date. Your changes are displayed with your logon ID.

  7. Position your cursor on the line containing your logon ID, then choose .
  8. The system displays the changes you have made (in this case the change to the plant-specific material status from 01 to BP in the relevant plant).

  9. Choose until the overview tree appears.