Perform Periodic Settlement for Project 
Menu Path |
Accounting ® Investment Management ® Investment Projects ® Period-End Closing ® Single Functions ® Settlement ® Individual Processing |
Transaction Code |
CJ88 |
Field |
Data |
WBS element |
XXXX-1 |
Settlement period |
Current month (for example 08) |
Posting period |
Current month (for example 08) |
Fiscal year |
Current year |
Processing type |
By period |
Detail list |
Select |
.If a dialog box appears, choose
.
.
.When settlement is successfully completed, you see a list of the settled amounts and receivers.
You see that 20% of the internal costs of WBS element XXXX-1 and, if you calculated interest, 100% of interest expense, was debited to cost center 4130. The remaining amount was settled to the asset under construction. Have a look at it.
.Menu Path |
Accounting ® Financial Accounting ® Fixed Assets ® Asset ® Asset Explorer |
Transaction Code |
AW01N |
You see the debit document and the origin (in this case the WBS element).
until the overview tree appears.