Display Report on Commitment and Actuals 
Menu Path |
Accounting ® Investment Management ® Investment Projects ® Information System ® Reports on Project Cost Controlling ® Costs ® Budget-Related ® Budget/Plan/Commitment/Rem Plan/Assigned |
Transaction Code |
S_ALR_87013558 |
If a dialog box appears, enter database profile 000000000001. If the Set Controlling Area dialog box appears, enter 1000.
Field |
Data |
Project |
Your project |
WBS element |
Empty |
Network/order |
Empty |
You see that actual costs in value category 400 resulted from the goods receipt of 15 steel girders. The remaining commitment is only for the two units that were not delivered yet.
In the Exit Report dialog box, choose Yes.
The two missing units will not be delivered. Therefore you set the indicator showing this in the purchase order. As a result the remaining commitment disappears.
Menu Path |
Logistics ® Materials Management ® Purchasing ® Purchase Order ® Change |
Transaction Code |
ME22N |

If your purchase order is not displayed automatically, choose
. In the Select Document dialog box, select Pur. order, enter your PO number, then choose Other document. In order to make changes, choose
.
Look at the values again.
Menu Path |
Accounting ® Investment Management ® Investment Projects ® Information System ® Reports on Project Cost Controlling ® Costs ® Budget-Related ® Budget/Plan/Commitment/Rem Plan/Assigned |
Transaction Code |
S_ALR_87013558 |
Field |
Data |
Project |
Your project |
WBS element |
Empty |
You see that the commitment has disappeared.
In the Exit Report dialog box, choose Yes.