Menu Path |
Accounting ® Investment Management ® Programs ® Information System ® Investment Management Reports ® Programs – Current Data ® Availability ® Budget Available for Measures |
Transaction Code |
S_ALR_87012825 |
If the system displays dialog boxes, confirm them.
Field |
Data |
Investment program |
Your program |
From position |
Empty |
Approval year |
Current year |
Fiscal year |
Current year |
.In the Assigned column, you see the commitment that was rolled up from the WBS element within the program hierarchy. (Assigned values are the sum of commitments and actuals. However, since there are no actuals yet in our case, the assigned values are the same as the commitment.)
You see the assigned values (in this case, the commitment) on the top WBS element, which is assigned to investment program position 111.
A dialog box appears.
.A measure report appears displaying all WBS elements and their values (budget/actual/commitment) on your project.
You see the costs of the selected WBS element, broken down by value category. (This is based on cost element and/or commitment items). In category 400 you see the commitment created by the purchase requisition.
A dialog box appears.
Copy.You see a list of line items in value category 400.
The original screen for purchase requisitions appears. There you have all the normal functions for purchase requisitions at your disposal.
until the overview tree appears.If the system displays dialog boxes, confirm them.