Budget Projects 

  1. Call up the transaction as follows:
  2. Menu Path

    Accounting ® Investment Management ® Investment Projects ® Budgeting ® Original Budget ® Change

    Transaction Code

    CJ30

  3. Enter the following data:
  4. Field

    Data

    Project def.

    Your project

  5. Choose .
  6. In the Timeframe field, choose Overall.
  7. First distribute the overall budget to the subordinate hierarchy levels.
  8. To distribute the overall values to the individual years, double click on the first position.
  9. To move between program positions, choose or .
  10. After you have made the distribution, choose .
  11. Choose .