Use
We have already created an analog measuring instrument as a piece of equipment. This needs to be checked every 30 days. You now create a maintenance plan for this purpose.
Procedure
Menu Path |
Logistics ® Plant Maintenance ® Preventive Maintenance ® Maintenance Planning ® Maintenance Plans ® Create ® Strategy Plan |
Transaction Code |
IP42 |
Field |
Data |
Description |
Maint. plan cat. |
Plant maintenance |
|
Strategy |
B |
Key date scheduling |
The Create Maintenance Plan: Strategy plan screen appears.
Field |
Data |
Description |
Maintenance plan text |
Calibrate multimeter |
|
Equipment |
10003540 |
Multimeter, analog |
Order type |
PM06 |
Calibration order |
Field |
Data |
Description |
Call horizon (%) |
90 |
Determines when the PM order should be generated for the maintenance call. |
Scheduling period |
365 |
The scheduling period during which the system generates maintenance calls. |
Start of cycle |
One month before today’s date |
The system generates a maintenance order from the maintenance plan every 30 days, so you set the cycle start one month in the past. This ensures that an order is available after scheduling. |