Subcontracting Procedure 

Prerequisites

Process Flow

  1. If a requirement exists for the finished product or assembly, the planning run generates a purchase requisition with item category L (subcontracting) or a planned order with special procurement Subcontracting. This planned order is converted into a purchase requisition with item category L.
  2. You can see the item category or the special procurement type when you display the MRP element in the stock/requirements list or in the MRP list.

  3. At the same time, the system explodes the BOM for the finished product or the assembly. Dependent requirements for the components are generated at finished product level either at the start date of the planned order or at the release date of the purchase requisition.
  4. These dependent requirements are included in the net requirements calculation as special dependent requirements (MRP element SubReq). However, if you make changes to quantities or dates, you can do so in the same way as for normal dependent requirements.

  5. The system then determines the source of supply, that is, the subcontractor, using the source list or quota arrangement and source list (see also Determining the Source of Supply for External Procurement).