Execute Capacity Leveling in Planned Order
Prerequisites
You have created a planned order or accessed a planned order in order to change or display it and are in the main screen of the planned order.
Procedure
The Settings for capacity planning dialog box now appears.
The system executes the lead time scheduling and calculates the capacity requirements using the parameters, that you have set in Customizing for MRP in the IMG activity Define scheduling parameters for planned orders.
If errors occurred during scheduling, the system displays an overview of the scheduling errors relating to the planned order. In the scheduling log, you can check the details of the scheduling errors.
Result
You now branch into the screen for capacity leveling (order view).
For the planned order selected, the capacity leveling relates to one work center and one capacity category (machine or person) as well as the capacity unit (for example, hours) from the work center. The system displays the following data:
Capacity loads caused by the planned order selected are highlighted.