Change Planned Order 

Use

Changes to existing planned orders can be necessary, for example, if the planned order in question is firmed, but then receives a rescheduling proposal during the planning run.

Procedure

  1. Starting from the Material Requirements Planning node, choose Planned order ® Change.
  2. The initial screen for changing a planned order now appears.

  3. Enter the number of the planned order to be changed and choose .
  4. The detail screen for changing a planned order now appears.

  5. Make the changes necessary.
  6. Save the changes.

If you change a planned order, it is then regarded as firmed for the planning run, (as is a planned order that is created manually). Thus, it will not be changed automatically during subsequent planning runs.