Manual Firming Date 

Use

You can protect procurement proposals from any automatic changes to master schedule items in the planning run in the near future by using the manual firming date. The system does not change procurement proposals automatically up to this date.

You define the manual firming date on a material-specific basis in the following places:

You can firm all types of procurement proposals with the manual firming date:

Features

The following applies to the firming type:

If you have defined a planning time fence, the following applies: